HE Parker multi-sports complex
Share HE Parker multi-sports complex on Facebook
Share HE Parker multi-sports complex on Twitter
Share HE Parker multi-sports complex on Linkedin
Email HE Parker multi-sports complex link
Consultation has concluded
HE Parker Multi- sports complex is really taking shape! Check out our slider image below!
So far the following works have been completed:<
- Bulk earthworks completed to northern and eastern side of retaining walls
- Wall cladding to indoor stadium completed
- Roof plant platform completed
- Internal partitions (walls) in progress
- Front forecourt retaining walls completed
- Electrical, hydraulic (plumbing) and mechanical (air conditioning/heating) rough in progressing
- Ceiling frame installation and plasterboard lining progressing
- 3 No. windows to southern wall of stadium cut out.
- Internal bench seating frame commenced to showcourt
- Light installation commenced to indoor stadium and commissioning in progress
- Installation of the Glulam timber beams for the front façade of the building
- Lift installation completed, awaiting final commissioning and internal finished
- Fire tank installation commenced in the undercroft
- Fencing to southern court completed
- Internal glass installation in progress
- Tiling commenced to wet areas (showers/toilets)
We will be providing further updates as the project progresses further. Make sure you visit again soon, or if you would like to receive an email notification from us that a new update has been added, please leave your details by clicking on the 'stay informed' button.
Maroondah City Council acknowledges the support of the Australian Government and the Victorian Government.